Last Planner® System and Percent Plan Complete: An Examination of Trade Contractor Performance.
W Power, D Taylor
Lean Construction Journal, 2019
192019
Evaluating the efficacy of a dedicated last planner system facilitator to enhance construction productivity
W Power, D Sinnott, P Lynch
Construction Economics and Building 21 (3), 142-158, 2021
162021
Agent-based modelling and simulation of construction crew performance
L Shehab, A Ezzeddine, F Hamzeh, W Power, I Tommelein, E Daniel
Proc. 28th Annual Conference of the International Group for Lean …, 2020
92020
CCC_implementing the construction control room on a fast-paced project: the case study of the Beirut port explosion
A Ezzeddine, L Shehab, I Srour, W Power, E Zankoul, E Freiha
International Journal of Construction Management 23 (5), 745-755, 2023
82023
Improving Commissioning and Qualification Delivery Using Last Planner System®.
W Power, D Sinnott, A Mullin
Lean Construction Journal, 2021
72021
Last planner® system and planned percent complete: An examination of individual trade performances
W Power, D Taylor
Proceedings of the 27th Annual Conference of the International Group for …, 2019
72019
Last Planner® System Implementation Health Check
W Power, D Sinnott, P Lynch, C Solorz
Proc. 29th Annual Conference of the International Group for Lean …, 2021
22021
An Evaluation of the Lookahead Planning Function in Last Planner® System
W Power, D Sinnott, P Lynch, C Solorz
Proceedings of the 31st Annual Conference of the International Group for …, 2023
12023
Construction Control Room for Project Monitoring and Control
A Ezzeddine, L Shehab, I Srour, W Power
Proceedings of the Creative Construction e-Conference, 2020-01, 2020
12020
SCRUM COMPLEMENTING LAST PLANNER SYSTEM–A CASE STUDY
W Power, D Sinnott, P Lynch
1
SCRUM’S DISTINCT ROLE DEFINITION COMPLEMENTING LPS & TAKT IMPLEMENTATION
W Power, D Sinnott, P Lynch
ACCELERATING CONSTRUCTION PROJECT DELIVERY USING AGILE'S INTEGRATED SYSTEM OF PRINCIPLES AND METHODS
W Power, D Sinnott, P Lynch
Thirty-Eighth ANNUAL CONFERENCE, 481, 0
系统目前无法执行此操作,请稍后再试。
文章 1–12